This phase is 50% occupied, homes and lots are available.
PHASE 7 (138 lots):
First group of homes under construction to be completed Spring 2024.
PHASE 11 (102 lots):
Infrastructure should be completed by the end of May 2024.
HARTFIELD CLUBHOUSE/AMENITIES:
The clubhouse and pool located in Phase 2 are estimated to be completed by Summer 2024 . Construction of the basketball half court and children’s playground will begin once the clubhouse and pool are completed.
TOWN CENTER/COMMERCIAL:
Land planning and civil engineering continues. Business owners interested in opening locations in Deer Moss Creek® should contact Dora Cawood at 850-678-2223 or email dcawood@ruckelproperties.com.